PERMITS
Please remember, certain loads can only obtain permits if the transport company can prove that transport by road is the only viable option after studying alternative options such as water.
Length |
18.75m>
<30.00m (Rigid) |
2 working days |
30.00m> (Rigid) |
8 weeks |
Width |
Width 3.00m>
<5.00m |
2 working days |
5.00m>
<6.10m |
2 weeks |
6.10m> |
8 weeks |
Weight |
<44.000kg |
2 working days |
44.000kg>
<150.000kg |
5 working days |
150.000kg> |
8 weeks |
|
|